8-18-2007


Windows arrive! (118kb) Installed window. Alumninum clad exterior, wood interior. (67kb) A room waiting for drywall an insulation. (59kb) The front with most windows installed. (103kb) Drywall (45kb)
4.jpg (47kb) Restroom & closet before drywall (73kb) Restroom & closet after drywall (32kb) The hallways have become dark as the drywall is put up! (66kb) One of the heating and cooling units that will be set up for each monks room. (60kb)
Bathroom ceiling above the shower. Vent shows above linen closet. (66kb) Orange sprinkler system pipe & blue and grey cabling. (67kb) 1st floor hallway celing (45kb) Two rooms on the top floor. Framing mostly done. (76kb) Rolls of insulation for the walls. (74kb)
Wood beams in the community room. (56kb) A vertical beam was recently put in place (62kb) The walls of the laundry room in the basement are being constructed. (49kb) Phone, computer, and tv cablling come together in a small room in the basement. (66kb) A small Dishwasher room is constructed in the basement. (51kb)
Brick work is progressing in the back of the abbey. (Southside) (85kb) Metal being placed on the roof before shingling begins. (83kb)