January
3, 2007, Wednesday
The
last several weeks work has continued to progress. Constructing
the rebar framework was quite interesting. It was entertaining
to observe as the workers climbed the springy wall
of steel to
tie it all together. It took quite
a while also to clean and prepare the forms and put them in place
for the first wall. Pre-made steel reinforced forms were used
for
the straight parts while wooden forms were hand crafted for the
zigs and zags of the walls. The additions first wall was poured
on Friday the 29th of December. It was
a rather
damp
overcast
day.
Not
ideal
for
working
in; rock
even needed to be spread so that the cement trucks would have solid
ground to park on while the cement was poured. A pump truck was
used to pour the cement into the wall forms. It took five or six
truckloads to complete the days project. Pouring took approximately
3 hours.
Shortly after the work was completed it changed from mist and drizzle
to rain. Over New Years weekend we received about 5 inches of snow
on top of an inch of rain so this next weeks work is rather muddy.
The forms are being removed now and set in place for the next
pour
it will take several rounds to complete the basement. The first
sets of pours are relatively simple because there are no windows
or doors in those sections; they are the unexposed walls of the
walk out basement. Check out the Three new video clips
of the creation of footings, building the forms, and pouring
the
wall.
|