March
15, 2007, Thursday: Steady Progress
Being Made
The snow is gone
and the "Hole" has dried out a lot this week with temperatures
reaching as high
as
80° although
a few snowflakes were in the air this morning. The site supervisor
said they may have to dig out some of the remaining mud from the
interior rooms because the moisture is trapped and taking to long
to dry. The periphery though is much improved.
The block work
has been making good progress as has the "free standing" wall
(roll your mouse over the picture from last weeks log to see the
changes).
The
delivery of steel has begun. Steel Lintels for the doors and windows
will
need to be installed
before completing the block work on the basement. Steel supports
will also soon be installed
to support the placement of the prefabricated concrete floor
that will start to be installed next week. The first pour
of the "free standing" wall was completed and the preparation
of the forms for the second level is almost ready. The wall will
be
capped with a peak and circular window. The form for that third
level is being built in the shop offsite. What you currently see
in photographs will be about 12 feet taller once the "peak" has
been added.
A new area of
the project was begun this week, the drilling of geothermal wells.
The heating and cooling system will use 30 wells that are each
300 foot deep. This will be very efficient and conserve
energy.
March
9, 2007, Friday: In
Like A Lion - Out like a Lamb?
March stormed
its way in. Literally! On March 1st we received the first real
blizzard in about 10 years. The January and February snows
had just melted and the construction site was starting to dry
out and then... 12 inches of snow. The next
Monday though saw the workers return to work and continuing
to lay cement blocks despite the new snow and accompanying
mud.
Work obviously
hasn't been progressing as fast as it could if things were
dry but work is progressing. Most of the basement blocks are
set and they are now preparing to pour a portion of the free
standing wall of the community room/dining room. Once they
have that done they can work the basement level blocks up to
the newly formed wall and then the placement of the 1st floor
will take place. I hope to get some good photos and video of
that process. Speaking of which I just recently put a new video
online featuring the block work and snowfall. More photos
were also added.
The current
weather forecast looks good for the foreseeable future. It
should be dry with temperatures in the 50's and 60's. Construction
should really
take off these next couple of weeks. Hopefully the blizzard
at the start of the month will mean it will be nothing but
lambing weather here on out.
|