June 15, 2007 Friday: Roof & Bricks Oh! My!
On Monday the
final section of the “free-standing” wall
was poured and the first bricks
arrived. Tuesday was spent mainly
in preparation for installing the trestles for the roof.
Wednesday the roof was started and the first bricks were laid on
the northeast
corner of the building. Then it rained! The workday was cut a few
hours short.
Thursday saw
most of the trestles
installed on the central/main portion of the
building and the masons continued to make progress.
The first bit of plumbing was laid in place and more and more conduit
is being installed inside. Lots of activity. More of the same
for days to come.
Added 3 Videos & 1 Slide Show
June
8, 2007 Friday: Physical Structure Nearing Completion.
Tuesday
they poured the second floor. They currently are preparing the
form
for the last section of the free standing wall
which was scheduled to be poured Friday but 2 days of very high winds
have made work difficult and prevented putting the last panels
to be set in place. The trestles for the roof arrived the end of
last
week
and
should
start
to go
up
in
the near
future. OPPD
was out and ran lines through the conduit
they set in last winter to the new transformer
that was recently installed
on the southeast corner or the addition. The main electrical
panel in the basement was also mounted onto the wall.
The
crew that is doing the internal
wall framing has started installing some of the door frames for
the rooms.
Even with this
activity the works site seems strangely quiet because the masons
are gone. The only block work left will be the small areas
that will connect to the free standing wall.The arrival of bricks
is currently scheduled for early next week presuming the demo
they constructed today meets with approval. I presume the masons
will return and start to lay the bricks next week. Other than the
basement
floor, the only cement work left for the actual structure is a small
portion of the
connection
piece on the second floor a couple of stairwell landings and the
step surfaces. The foundation was poured for the stoop of the stairwell
and a footing for a 2 story steel post that will support a roof over
the stairwell entrance. Footings & stoops for the main entrance
to the
addition and patio also remain.
The basement
is still mud and harbors a few small ponds but recent dry weather
has helped some.
Soon
a roof and bricks! Big changes in appearance are on the horizon!
New
Slide Shows added!
|