October
18, 2007 – Thursday; Fireplaces done, Elevator started.
It
is a good thing that much of the focus for construction has moved
inside
because we have received over 5 inches or rain this week. They
were suppose to start dirt work 2 weeks ago but It might be another
week or more before they can proceed. Isn't October suppose to
be a dry month?
Both the basement
fireplace in the dining room and the upstairs
fireplace in
the community room have been completed. They look great. The brick
layers showed
true
craftsmanship
in tapering the community room chimney. They should be able to
begin framing the walls in these two areas once they are cleaned
up and
the elevator is completed. Speaking of which... The piston is
installed in its subterranean tube, the rails are installed on
the sides of the shaft and the frame has been installed. The power
supply for the elevator has also been installed in the basement
across from the shaft. It is a good start so far this week!
In the private
rooms drywall is being plastered and sanded on a daily basis the
only slow down is that they are ripping the ceiling out of the
bathrooms to reinstall the heating/cooling
vents. They mistakenly
put in vents with out sound installation. This redo is going smoothly.
Upstairs the dry wall is making very good progress and most
of the hanging should be completed by the end of the week. The
basement has had some drywall hung and lots of framing done.
Lets hope for
dry weather so the ground can be worked and the sidewalks, parking,
and road can be done before winter sets in. Also the deck & patio
need to be constructed off the dining room and community rooms.
October
8, 2007 – Monday; Exterior Bricks done, New
Completion Date Set
The last of the bricks have been set in place on the exterior of
the new addition. The masons have also completed their work on the
dining room fireplace and are now working on the large fireplace
and chimney in the community room. It should probably be done by
the end of the week.
Drywall work is progressing fast. They have started taping the private
rooms on the 1st floor and are working some on the top floor. The
communal areas will have to wait for a while. The only thing that
is a running a bit behind is the electrical. It is hoped that with
a little extra help they will soon be caught up.
Lower Level
The basement is seeing lots of plumbing and mechanical work taking
place. This is sort of the “core” area for this work
since the mechanical room is located in the basement. They are
progressing nicely. The framing of interior walls is even beginning
in the basement.
Dirt Work!
Today they will begin plotting the contours, drainage, and prep work
for the parking, road, and sidewalk.
Fire Marshall
The Fire Marshall has determined that we must either put a sprinkler
system into the existing Abbey building or build an additional
road to within 100 feet of the building. It will need to be large
enough for fire trucks to turn around. We have 1 year to decide
on which way we want to go. They are both an additional expense
we had not counted on. If we build the road, most of the trees
in front of the abbey would need to be removed. We also would have
the additional loss of our front yard being turned into asphalt.
Sprinklers might be preferable but might be cost prohibitive.
Completion -
Completion Schedule: PDF file
A new completion date has been determined. It is December 31st. Happy
New Year!
September
11, 2007 - Tuesday; Exterior nearing completion
The roof of the
addition is now attached to the abbey. The shingles are now all
in place. Most of the windows in the living quarters are installed
and the brick work has moved to the "community and dining
room areas.
Monastic
rooms: The monks rooms have almost all
electrical and plumbing, and mechanical work completed in the
rooms. There are now allot of wires dangling
in
fuse boxes to be connected. This type work should soon be shifting
to the basement, and community room areas.
Drywall: The
last of the water damaged drywall and insulation is removed. Soon
dry walling should resume after a three week pause to get
the building sealed up. This step will take a lot of time, there
are a lot of walls and ceiling space to be covered, plastered
and sanded!
Other Items: Recently
the cap on the chimney was installed so that the last of shingling
could be completed.
The last steps of the stairwell have been cemented. The floor
in the dining room in the basement is getting close to being ready
to be poured. That would complete all cement work in the addition.
The windows and doors for the basement, Dining Room, and community
room are on site and waiting to be installed. Parking
and Road: The current issue is paving.
We would like to have our parking directly
east
of the
end of the building. There is some concern we will have to put
a drive all the way up to the abbey's primary entrance in the existing
building to appease fire officials. We really don't want a road
(or its expense) in the middle of our
front yard. A front lawn looks best as green grass not concrete!
So hopefully something can be worked out.
I've
added a Panorama
of the south side to Photos Section. |