February 8,
2008 - Friday; Almost but not Quite Finished!
The addition
is nearly complete! The tile has been set except for a six square
foot area in the basement where they ran out of tile. It should
arrive soon. The private rooms are going through their
2nd round of checklists. The ceiling panels have been installed
on the 1st and 2nd floors.
Today they
should be working on installing the carpet in the community room.
The electrical work is focusing on finishing the elevator work
and then the last of the community room light fixtures and switches
need to be completed.
Two things they
are waiting on is the hallway carpet to be delivered and the railing
for the deck. They had
to redo the carpet order because the company messed up and didn't
get the color correct so it had to be manufactured again.
It should
arrive next week. The railing is currently being made offsite
and should be ready in a week or so.
The touch up
work in the basement hasn't gotten very far yet but it should make
headway next week. The outdoor lighting along the drive & sidewalks
is a low priority and will be worked on later as the snow melts
and it warms up. The retaining walls in back will also be extended
in the spring after the ground thaws. Neither of these should interfere
with the building inspection and clearance for the monks to move
to their new rooms.
Moving
Date? Hopefully spring break if things
are ready. We need the blinds to be installed and new beds to
arrive. Abbot Michael has encourage the monastic community to
go through the addition sometime during this past week or next
week and start thinking about what rooms they would
like. After that a list will go around for the monks to start picking
rooms according to seniority. |